Probabilistic Scheduling Based On Hybrid Bayesian Network–Program Evaluation Review Technique,

Tri Joko Wahyu Adi, Farida Rachmawati, Safira Yulia Rizky

Abstract


Project scheduling based on probabilistic methods commonly uses the Program Evaluation Review Technique (PERT). However, practitioners do not widely utilize PERT-based scheduling due to the difficulty in obtaining historical data for similar projects. PERT has several drawbacks, such as the inability to update activity dura- tions in real time. In reality, changes in project conditions related to resources have a highly dynamic nature. The availability of materials, fluctuating labor productiv- ity, and equipment significantly determine the project completion time. This research aims to propose a probabilistic scheduling model based on the Hybrid Bayesian Network-PERT. This model combines PERT with Bayesian Network (BN). BN is used to accommodate real-time changes in resource conditions. The modeling of BN diagrams and variables is obtained through an in-depth literature review, direct field observations, and distributing questionnaires to experts in project scheduling. The model is validated by applying the proposed model to a 60 m concrete bridge construction project in Indonesia. The simulation results of the proposed model are then compared with the case study project to assess the model’s accuracy. The result of the study shows that the proposed hybrid Bayesian-PERT model is accurate and can eliminate the weaknesses of the PERT method. Besides being able to provide an accurate prediction of project completion time (93.4%), this model can also be updated in real-time according to the actual condition of the project

Keywords


Bayesian Network; Construction Risk; PERT; Productivity; Project Scheduling

Full Text:

Full Text

References


Jin Y, Zhao Z. The project schedule management model based on the program evaluation and review technique and Bayesian networks. IEEE International Conference on Automation and Logistics, ICAL 2011;p. 379–383.

Akpan NP, Agadaga GO, Cruz-Suárez H. Modelling Building Renovation Using PERT. Asian Research Journal of Mathematics 2020 4;16(4):25–38. https://journalarjom.com/index.php/ARJOM/article/view/324.

Simankina T, Kibireva I, Mottaeva A, Gusarova M. Application of the PERT Method in Scheduling of Construction of Apart-Hotel for Energy Consumption Economy. Advances in Intelligent Systems and Computing 2019;983:138–145.

de Melo ACV, Sanchez AJ. Software maintenance project delays prediction using Bayesian Networks. Expert Systems with Applications 2008 2;34(2):908–919.

Qiao C. Project Completion Probability Analysis Based on Bayesian Network. Academic Journal of Engineering and Technology Science 2021 1;4(1):62–69.

Rezakhani P. Hybrid fuzzy-Bayesian decision support tool for dynamic project scheduling and control under uncertainty. International Journal of Construction Management 2020;22(15):2864–2876. https://www.tandfonline.com/doi/abs/10.1080/15623599.2020.1828539.

Habibi F, Birgani OT, Koppelaar H, Radenović S. Using fuzzy logic to improve the project time and cost estimation based on Project Evaluation and Review Technique (PERT). Journal of Project Management 2018;p. 183–196.

Agyei W. Project Planning And Scheduling Using PERT And CPM Techniques With Linear Programming: Case Study. International Journal of Scientific & Technology Research 2015;4(8):222–227. www.ijstr.org.

Nguyen NT, Huynh QT, Vu THG. A Bayesian critical path method for managing common risks in software project scheduling. ACM International Conference Proceeding Series 2018 12;p. 382–388. https://dl.acm.org/doi/10.1145/3287921.3287962.

Refaie AMA, Alashwal AM, Abdul-Samad Z, Salleh H. Weather and labor productivity in construction: a literature review and taxonomy of studies. International Journal of Productivity and Performance Management 2021 3;70(4):941–957.

Jalal MP, Shoar S. A hybrid framework to model factors affecting construction labour productivity: Case study of Iran. Journal of Financial Management of Property and Construction 2019 10;24(3):630–654.

Alaghbari W, Al-Sakkaf AA, Sultan B. Factors affecting construction labour productivity in Yemen. International Journal of Construction Management 2017 1;19(1):79–91.

Jarkas AM, Balushi RAA, Raveendranath PK. Determinants of construction labour productivity in Oman. International Journal of Construction Management 2015 10;15(4):332–344.

Chigara B, Moyo T. Factors Affecting Labor Productivity on Building Projects in Zimbabwe. International Journal of Architecture, Engineering and Construction 2014 3;3(1):57–65.

Thomas AV, Sudhakumar J. Factors Influencing Construction Labour Productivity: An Indian Case Study. Journal of Construction in Developing Countries 2014;19(1):53–68.

Adam A, Josephson PE, Lindahl G. Implications of Cost Overruns and Time Delays on Major Public Construction Projects. In: Proceedings of the 19th International Symposium on Advancement of Construction Management and Real Estate Springer, Berlin, Heidelberg; 2015. p. 747–758. https://link.springer.com/chapter/10.1007/978-3-662-46994-1_61.




DOI: http://dx.doi.org/10.12962/j20882033.v34i2.16693

Refbacks

  • There are currently no refbacks.


Creative Commons License

IPTEK Journal of Science and Technology by Lembaga Penelitian dan Pengabdian kepada Masyarakat, ITS is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Based on a work at https://iptek.its.ac.id/index.php/jts.